One of the most common questions we get after “how much” is “how long” — understandably, since most people want to know when they’ll actually stop worrying about KPLC outages. Here’s a realistic breakdown of the process from first contact to switch-on.
Step 1: Site Assessment (Same Week)
A technician visits your property to assess roof condition, orientation, shading, your electrical panel, and your typical appliance load. This is also when you’ll discuss on-grid, off-grid, or hybrid, and any budget constraints. At Stream Solar this first visit is free.
Step 2: System Design and Quotation (2–5 Days)
Based on the site visit, the installer designs a system sized to your actual usage — not a generic package — and provides a detailed quote covering panels, inverter, battery (if applicable), mounting, wiring, and labour.
Step 3: Approval and Deposit (Your Timeline)
Once you approve the quote, most installers require a deposit before ordering equipment. For standard system sizes using stock components, this step can move quickly; custom or large commercial systems may take longer if specific equipment needs to be sourced.
Step 4: Procurement (3–14 Days)
Panels, inverters, batteries, and mounting hardware are sourced. If everything is in stock locally, this is fast. Larger or highly specific commercial/industrial orders can take longer, particularly for custom battery capacities.
Step 5: Installation (1–3 Days for Most Homes)
For a standard residential system, physical installation — mounting panels, running wiring, installing the inverter and battery, connecting to your distribution board — typically takes one to three days depending on system size and roof complexity. Commercial and industrial installations take longer depending on scale.
Step 6: Testing and Commissioning (Same Day as Installation, Usually)
Before switch-on, the system is tested for safe operation: correct wiring, earthing, inverter settings, and (for hybrid/off-grid systems) battery charge/discharge behaviour. This is also when EPRA-compliant protection equipment is verified.
Step 7: Grid Interconnection (If Applicable)
For grid-tied and hybrid systems, interconnection approval may be required before the system is permitted to feed back into the KPLC network, depending on system size and setup. Your installer should handle this paperwork, not leave it to you.
Step 8: Handover and Walkthrough
You should receive a walkthrough of how the system works, how to read any monitoring app, warranty documentation for panels and inverter, and maintenance guidance (typically occasional panel cleaning and an annual check).
What Can Slow Things Down
- Roof reinforcement or repairs needed before mounting can begin
- Custom battery capacity or specific equipment not held in local stock
- Weather delays during the physical installation days
- Commercial/industrial projects requiring additional structural or electrical engineering sign-off
Realistic Expectation
For a typical residential hybrid system in Nairobi, most homeowners go from first site visit to a working system within a few weeks, assuming standard components. Larger commercial projects naturally take longer. Be wary of any installer promising same-week installation on a custom system — that’s usually a sign of corners being cut somewhere.
Start the Clock
Book your free site assessment and we’ll give you a specific timeline for your property, not a generic estimate.